Botany Greenhouse
Location:
Gainesville, Florida
Contract Amount:
$127,016.00
Final Contract:
$337,341.55
Current Phase:
100% Complete
Completion Date:
November 8, 2001
Service Provided:
CM at risk with GMP
Owner:
 University of Florida - Health Center
Owner Contact:
Ralph Giro
Owner Phone Number:
352.392.1551
Engineer:
Moses & Associates
Engineer Contact:
Frank Moses
Engineer Phone Number:
352.372.1911
Description:          
New 3,325 SF greenhouse facility. Project included extensive sitework, retaining wall, site electrical and water main extensions. Greenhouse features four bays with an attached head house. One greenhouse bay is air conditioned to allow for temperate zone plants. All greenhouse bays have evaporative cooling systems, horizontal flow fans, retractable shade cloth ceilings, computer controls for each bay. All bays have grow lights at are controlled by timers.

Correlation:  Recent, UF-IFAS Minor Projects CM project,  Highlights our experience in greenhouse construction.  Five proposed team members worked on this project. Brent Taylor - Project Manager, Ralph King - Project Superintendent, Nancy Taylor - Project Coordinator, Kevin Odom - Labor, Brian Melton - Labor.